Reducing the energy intensity of pressurized air production at the Pumping Station 1 and increasing the reliability of pressurized air supplies to the Třinecké železárny network
Subject of realization
Replacement of unsuitable turbochargers ČKD 1 and IRMA at the Pumping Station 1 (high energy intensity, consumption size, speed of pressure regulation in the network, and supply security)
Outage and disassembly of the ČKD 5 turbocharger
Supply of modern sources of pressurized air—Atlas Copco EK1, EK2, and EK3 turbochargers operating in the required control range with the highest possible efficiency to achieve lower