Tomorrow, on Saturday July 19 at 01:00 o'clock, Unit 2 will be for a short time disconnected from the distribution grid. The reason of the electricity production interruption is a repair of the drain line under the high pressure turbine. The reactor power will be reduced and stabilized at the level of 35 % RTP. The repeated unit synchronization with the power distribution grid is scheduled for the same day, i.e. Saturday July 19 at 11 o'clock. Hence, the Temelín Unit 2 will interrupt its electricity production for about ten hours.
Information on parameters at Unit 1 today on July 18, 2008 at 10:00 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1014 MWe
- Electricity production since the beginning of the year: 4 156 938 MWh
Information on parameters at Unit 2 today on July 18, 2008 at 10:00 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1010 MWe
- Electricity production since the beginning of the year: 3 415 165 MWh
Václav BROM
ČEZ Group Spokesman
Nuclear Power Plant Temelín