3. 8. 2009

Information on NPP Dukovany 03/08/2009

Units 1, 2, 3, 4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 302 321 607 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 454 MWe

Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 448 MWe

Unit 3 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 488 MWe

Unit 4 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output - 450 MWe

 

Electricity production since the beginning of the year:  8 169 759 MWh.

 

Ing. Petr Spilka

Spokesman of the ČEZ Group

Nuclear Power Plant Dukovany