6. 4. 2010

Information on NPP Dukovany 06/04/2010

Units 1, 2, 4 are operated at full rated power. Unit 3 is in a startup mode after refuelling. All auxiliary systems are working in accordance with operational needs of units. El. production since the beginning of operation: 311 900 310 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

  • Unit 1 is in Mode 1 – power conditions, Reaktor power is 100 %, Turbine generator output – 464 MWe
  • Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 463 MWe
  • Unit 3 is in Mode 1 – The Unit is in a startup mode after refuelling. Reaktor power is 18,4 %,
  • Turbine generator output – 0 MWe
  • Unit 4 is in Mode 1 – power conditions, Reactor power is 100 %, Turbine generator output – 465 MWe

 

Electricity production since the beginning of the year:  3 793 344 MWh.

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany