Information on NPP Dukovany 15/12/2009

Units 1, 2, 3 are operated at full rated power. Unit 4 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 307 407 120 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

  • Unit 1 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 468 MWe
  • Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 462 MWe
  • Unit 3 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 487 MWe
  • Unit 4 is in Mode 3 - hot standby state

 

Electricity production since the beginning of the year:  13 255 272 MWh.

 

Ing. Petr Spilka
Spokesman of the ČEZ Group