21. 7. 2009

Information on NPP Dukovany 21/07/2009

Units 1, 2, 3, 4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 301 757 053 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 455 MWe

Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 452 MWe

Unit 3 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 492 MWe

Unit 4 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output - 460 MWe

 

Electricity production since the beginning of the year:  7 605 205 MWh.

   

Ing. Petr Spilka

Spokesman of the ČEZ Group

Nuclear Power Plant Dukovany