5. 8. 2010

Information on NPP Dukovany 5/8/2010

Units 1, 2, 3, 4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 317 020 898 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

 

  • Unit 1 is in Mode 1 – power operation, Reaktor power is 100 %, Turbine generator output – 456 MWe
  • Unit 2 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 450 MWe
  • Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output – 493 MWe
  • Unit 4 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 453 MWe

 

 

Electricity production since the beginning of the year:  8 913 932 MWh.

 

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany