2. 1. 2006
Information on NPP Temelín 1/2006
Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 980 MW
· Electricity production since the beginning of the year: 13 573 MWh Information on parameters at Unit 2 today on January 2, 2006 at 07:30 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 86 %
· Turbine generator output – 817 MW
· Electricity production since the beginning of the year: 19 364 MWh Milan Nebesář
Spokesman of the Temelín NPP