31. 5. 2018

INFORMATION ON NPP TEMELÍN 103 / 2018

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output – 1071 MWe
  • Electricity production since the beginning of the year: 2 321 189 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1078 MWe
  • Electricity production since the beginning of the year: 3 920 294 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín