INFORMATION ON NPP TEMELÍN 105 / 2019

Both Unit 1 and 2 are in operation at planned power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output – 1069 MWe
  • Electricity production since the beginning of the year: 2 466 354 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1078 MWe
  • Electricity production since the beginning of the year: 4 045 145 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín