17. 1. 2008

Information on NPP Temelín 12 / 2008

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on January 17, 2008 at 07:45 o‘clock:

  • Unit is in Mode 1 -  power operation
  • Reactor power is 100 %
  • Turbine generator output - 1011 MWe
  • Electricity production since the beginning of the year: 388 150 MWh

Information on parameters at Unit 2 today on January 17, 2008 at 07:45 o‘clock:

  • Unit is in Mode 1 - power operation 
  • Reactor power is 100 %
  • Turbine generator output - 1003 MWe
  • Electricity production since the beginning of the year:  358 745 MWh

 

Marek Sviták
Spokesman of the ČEZ GROUP
Temelín NPP