21. 6. 2022

INFORMATION ON NPP TEMELÍN 120 / 2022

Both Unit 1 and 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in the operation
  • Turbine generator output – 1085 MWe
  • Electricity production since the beginning of the year: 3 054 159 MWh

 

Information on parameters at Unit 2:

  • Unit is in the operation
  • Turbine generator output - 1088 MWe
  • Electricity production since the beginning of the year: 4 502 814 MWh