1. 8. 2022

INFORMATION ON NPP TEMELÍN 147 / 2022

Unit 1 is in operation at full rated power. Unit 2 is in the planned outage for refuelling. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in the operation
  • Turbine generator output – 1075 MWe
  • Electricity production since the beginning of the year: 4 118 721 MWh

 

Information on parameters at Unit 2:

  • Unit is in the planned outage
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 5 284 307 MWh