5. 8. 2019

INFORMATION ON NPP TEMELÍN 146 / 2019

Unit 2 is in the planned outage for refuelling. Unit 1 is in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output - 1059 MWe
  • Electricity production since the beginning of the year: 4 029 661 MWh

Information on parameters at Unit 2:

  • Unit is in the planned outage
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 4 477 200 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín