17. 9. 2020

INFORMATION ON NPP TEMELÍN 182 / 2020

The Unit 2 is in the operation. The connection of the Unit 1 is currently being prepared. The unit was shut down from the transmission grid in the morning due to increased vibration of the turbogenerator.The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in the outage
  • Turbine generator output – 0 MWe
  • Electricity production since the beginning of the year: 4 978 382 MWh

 

Information on parameters at Unit 2:

  • Unit is in the operation
  • Turbine generator output - 1086 MWe
  • Electricity production since the beginning of the year: 5 256 842 MWh