29. 9. 2017

INFORMATION ON NPP TEMELÍN 189 / 2017

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on September 29, 2017 at 9:45 o‘clock:

  • Unit is in operation
  • Turbine generator output - 1078 MWe
  • Electricity production since the beginning of the year: 7 029 241 MWh

Information on parameters at Unit 2 today on September 29, 2017 at 9:45 o‘clock:

  • Unit is in operation
  • Turbine generator output - 1088 MWe
  • Electricity production since the beginning of the year: 5 171 039 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín