3. 1. 2020

INFORMATION ON NPP TEMELÍN 2 / 2020

Both Unit 1 and 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in the operation
  • Turbine generator output - 599 MWe
  • Electricity production since the beginning of the year: 0 MWh

Information on parameters at Unit 2:

  • Unit is in the operation
  • Turbine generator output - 1094 MWe
  • Electricity production since the beginning of the year: 52 394 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín