16. 10. 2017

INFORMATION ON NPP TEMELÍN 200 / 2017

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on October 16, 2017 at 9:00 o‘clock:

  • Unit is in operation
  • Turbine generator output - 1071 MWe
  • Electricity production since the beginning of the year: 7 469 418 MWh

Information on parameters at Unit 2 today on October 16, 2017 at 9:00 o‘clock:

  • Unit is in operation
  • Turbine generator output - 1086 MWe
  • Electricity production since the beginning of the year: 5 614 943 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín