2. 12. 2019

INFORMATION ON NPP TEMELÍN 230 / 2019

Both Unit 1 and 2 are in operation. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output - 1064 MWe
  • Electricity production since the beginning of the year: 7 050 106 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1095 MWe
  • Electricity production since the beginning of the year: 7 421 929 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín