30. 12. 2019

INFORMATION ON NPP TEMELÍN 247 / 2019

The Unit 2 in in operation. The Unit 1 is in the outage due to exchange of penetrations in the cooling system of the generator in the non-nuclear part of the power plant. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in outage
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 7 553 770 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1096 MWe
  • Electricity production since the beginning of the year: 8 157 460 MWh

  

Marek Sviták
Spokesman of the ČEZ Group