INFORMATION ON NPP TEMELÍN 36 / 2019

According to the plan Unit 1 operates in the power effect of reactivity mode. The Unit 2 is in operation at planned power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output - 1013 MWe
  • Electricity production since the beginning of the year: 1 328 287 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1093 MWe
  • Electricity production since the beginning of the year: 1 340 707 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín