27. 2. 2019

INFORMATION ON NPP TEMELÍN 40 / 2019

According to the plan Unit 1 operates in the power effect of reactivity mode. The Unit 2 is in operation at planned power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output - 959 MWe
  • Electricity production since the beginning of the year: 1 471 414 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1089 MWe
  • Electricity production since the beginning of the year: 1 498 247 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín