INFORMATION ON NPP TEMELÍN 80 / 2018

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output – 1084 MWe
  • Electricity production since the beginning of the year: 1 420 672 MWh

Information on parameters at Unit 2:

  • Unit is in operation
  • Turbine generator output - 1090 MWe
  • Electricity production since the beginning of the year: 3 010 460 MWh

 

Marek Sviták
Spokesman of the ČEZ Group