3. 5. 2007
Information on NPP Temelín 88 / 2007
Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 980 MWe
· Electricity production since the beginning of the year: 813 491 MWh Information on parameters at Unit 2 today on May 3, 2007 at 9:45 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 99 %
· Turbine generator output - 1009 MW
· Electricity production since the beginning of the year: 2 930 221 MWh Ing. Marek Sviták