17. 4. 2008

Information on Dukovany NPP, April 17th 2008

Units 1, 3, 4 are operated at full rated power. Unit 2 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. Electricity production since the beginning of operation: 283 735 722 MWh.

Information on parameters of Unit 1-4, today on  April 17th 2008at7:00hrs:

Unit 1 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 466 MWe

Unit 2 is in Mode 6 – refueling – shutdown with primary circuit open

Unit 3 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 466 MWe

Unit 4 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 468 MWe

 

Electricity production since the beginning of the year: 4 031 422 MWh.