22. 2. 2008

Information on Dukovany NPP, February 22nd 2008

Units 1, 2, 4 are operated at full rated power. Unit 3 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. Electricity production since the beginning of operation: 281 757 106 MWh.

Information on parameters of Unit 1-4, today on  February 22nd 2008at7:00hrs:

Unit 1 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 466 MWe

Unit 2 is in Mode 1 – power conditions: Reactor power is 97 %, Turbine generator output – 432 MWe

Unit 3 is in Mode 2 – startup-criticality achieving and reactor critical

Unit 4 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 454 MWe

 

Electricity production since the beginning of the year: 2 052 806 MWh.