11. 11. 2005

Information on Dukovany NPP, November 11

Units 1, 2, 3, are operated at full rated power. All auxiliary systems are working in accordance with operational needs of the units. Electricity production since the beginning of operation: 249 773 346

  Information on parameters of Unit 1 – 4, today on November 11, 2005 at 7:00 hrs:

· Unit 1 is in Mode 1 - power conditions: · Reactor power is 100% · Turbine generator output – 447.75  MWe

· Unit 2 is in Mode 1 - power conditions: · Reactor power is 100% · Turbine generator output – 445.42  MWe

· Unit 3 is in Mode 1 - power conditions ·  Reactor power is 100% · Turbine generator output – 462.03  MWe

· Unit 4 is in Mode 6 - power conditions: · Reactor is off, because of refuelling

· Electricity production since the beginning of the year: 11 745 417 MWh