Information on Dukovany NPP, November 6th 2007

Units 2,3,4 are operated at full rated power. Unit 1 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. Electricity production since the beginning of operation: 277 688 840 MWh.

Information on parameters of Unit 1-4, today on  November 6th 2007at 7:00hrs:

Unit 1 is in Mode 2 – startup-criticality achieving and reactor critical

 

Unit 2 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 434 MWe

 

Unit 3 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 464 MWe

 

Unit 4 is in Mode 1 – power conditions: Reactor power is 95,4 %, Turbine generator output - 447 MWe

Electricity production since the beginning of the year: 11 891 683 MWh.