Information on NPP Dukovany 10/03/2010

Units 1, 2, 4 are operated at full rated power. Unit 3 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El. production since the beginning of operation: 310 999 487 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

  • Unit 1 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 468 MWe
  • Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 462 MWe
  • Unit 3 is in Mode 6 - refueling – shutdown with primary circuit open
  • Unit 4 is in Mode 1 - power conditions, Reactor power is 100 %, Turbine generator output – 459 MWe

 

Electricity production since the beginning of the year:  2 892 521 MWh.

 