12. 11. 2010

Information on NPP Dukovany 12/11/2010

Units 1, 2 are operated at full rated power. Units 3, 4 are in planned outage. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 320 788 920 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

 

  • Unit 1 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 467 MWe
  • Unit 2 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 460 MWe
  • Unit 3 is in Mode 6 - refueling – shutdown with primary circuit open
  • Unit 4 is in Mode 7 – total fuel removal from reactor core

 

 

Electricity production since the beginning of the year:  12 659 553 MWh.

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany