14. 4. 2009

Information on NPP Dukovany 14/04/2009

Units 1, 3, 4 are operated at full rated power. Unit 2 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. Electricity production since the beginning of operation: 297 689 545 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 458 MWe

Unit 2 is in Mode 6 – refueling – shutdown with primary circuit open

Unit 3 is in Mode 1 – startup after Unit modernisation: Reactor power is 50 %, Turbine generator output – 176 MWe

Unit 4 is in Mode 1 – power conditions: Reactor power is 100 %, Turbine generator output – 460 MWe

 

 Electricity production since the beginning of the year:  3 537 697 MWh.

 

Ing. Petr Spilka

Spokesman of the ČEZ Group

Nuclear Power Plant Dukovany