19. 11. 2009

Information on NPP Dukovany 19/11/2009

Units 1, 2, 3 are operated at full rated power. Unit 4 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 306 517 256 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 467 MWe

Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 459 MWe

Unit 3 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 498 MWe

Unit 4 is in Mode 7 - total fuel removal from reactor core

 

 Electricity production since the beginning of the year:  12 365 408 MWh.

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany