11. 7. 2024

Information on NPP DUKOVANY 11/07/2024

Units 1, 3, 4 are in the operation. Unit 2 is in planned outage. Electricity production since the beginning of the operation: 513 711 244 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 485 MWe
Unit 2 is in Mode 7 - outage
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 500 MWe
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 484 MWe

Electricity production since the beginning of the year: 7 607 145 MWh.