7/14/2023
Information on NPP DUKOVANY 14/7/2023
Units 3, 4 are in the operation. Units 1, 2 are in the planned outages. Electricity production since the beginning of the operation: 499 541 435 MWh.
Information on parameters of Unit 1-4, today at 7:00 hrs:
Unit 1 is in Mode 7 - outage
Unit 2 is in Mode 6 - outage
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 468 MWe
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 490 MWe
Electricity production since the beginning of the year: 7 764 604 MWh.
News on the topic
Czech Nuclear Power Plants Comply with International Environmental Protection Standards