22. 4. 2010

Information on NPP Dukovany 22/04/2010

Units 1, 3, 4 are operated at full rated power. Unit 2 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El. production since the beginning of operation: 312 549 885 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

  • Unit 1 is in Mode 1 – power conditions, Reaktor power is 100 %, Turbine generator output – 469 MWe
  • Unit 2 is in Mode 6 – refueling – shutdown with primary circuit open
  • Unit 3 is in Mode 1 – power conditions, Reaktor power is  99,8 %, Turbine generator output – 503 MWe
  • Unit 4 is in Mode 1 – power conditions, Reactor power is 100 %, Turbine generator output – 466 MWe

 

Electricity production since the beginning of the year:  4 442 919 MWh.

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany