26. 8. 2009

Information on NPP Dukovany 26/08/2009

Units 1, 2, 3, 4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 303 340 076 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 453 MWe

Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 449 MWe

Unit 3 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output – 488 MWe

Unit 4 is in Mode 1 - power conditions: Reactor power is 100 %, Turbine generator output - 453 MWe

   

Electricity production since the beginning of the year:  9 188 228 MWh.

 

Ing. Petr Spilka

Spokesman of the ČEZ Group

Nuclear Power Plant Dukovany