Units 1, 2, 3 are operated at full rated power. Unit 4 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 320 254 246 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

 

  • Unit 1 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 467 MWe
  • Unit 2 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 463 MWe
  • Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output – 502 MWe
  • Unit 4 is in Mode 7 – total fuel removal from reactor core

 

 

Electricity production since the beginning of the year:  12 147 280 MWh.

 