Units 1, 2, 4 are operated at full rated power. Unit 3 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El. production since the beginning of operation: 311 536 016 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

  • Unit 1 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 464 MWe
  • Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 458 MWe
  • Unit 3 is in Mode 6 - refueling – shutdown with primary circuit open
  • Unit 4 is in Mode 1 - power conditions, Reactor power is 100 %, Turbine generator output – 464 MWe

Electricity production since the beginning of the year:  3 429 050MWh.

 