6. 6. 2006

Information on NPP Temelín 109/2006

Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of 1/4 of the reactor fuel.

June 6, 2006

Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of 1/4 of the reactor fuel. All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on June 6, 2006 at 07:30 o‘clock:
· Unit is in Mode 6
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 3 450 131 MWh

Information on parameters at Unit 2 today on June 6, 2006 at 07:30 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 981 MW
· Electricity production since the beginning of the year: 2 928 119 MWh

Milan Nebesář
NPP Temelín Spokesman