Yesterday, startup tests at the minimum reactor power level have been completed. The operations personnel increase the Unit 2 reactor power to 20% RTP. The turbine balancing will be carried out at this power level.
Information on parameters at Unit 1 today on June 25, 2008 at 9:00 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1006 MWe
- Electricity production since the beginning of the year: 3 600 419 MWh
Information on parameters at Unit 2 today on June 25, 2008 at 9:00 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 3 %
- Turbine generator output - 0 MWe
- Electricity production since the beginning of the year: 2 967 592 MWh
Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín