26. 6. 2007
Information on NPP Temelín 125 / 2007
The first Unit is operated at a planned power level. At Unit 2, the planned outage connected with the replacement of ¼ of fuel in the reactor is under way. All auxiliary systems of the power plant are working in accordance with the operation needs.
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 979 MWe
· Electricity production since the beginning of the year: 2 050 312 MWh Information on parameters at Unit 2 today on June 25, 2007 at 08:00 o‘clock:
· Unit is in Mode 6
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 2 975 006 MWh Marek Sviták
ČEZ Group Spokesman Nuclear Power Plant Temelín