18. 1. 2007

Information on NPP Temelín 13 / 2007

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems are working in accordance with the operation needs of individual units.

January 18, 2007

 Information on parameters at Unit 1 today on January 18, 2007 at 07:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 976 MWe
· Electricity production since the beginning of the year: 372 657 MWh

Information on parameters at Unit 2 today on January 18, 2007 at 07:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 99 %
· Turbine generator output - 1012 MWe
· Electricity production since the beginning of the year: 413 044 MWh

Milan Nebesář
Spokesman of the ČEZ GROUP Temelín NPP