10. 7. 2007
Information on NPP Temelín 133 / 2007
The first Unit is operated at a planned power level. At Unit 2, the reactor power has been stabilized on 30 % RTP and, today, the planned physics tests will be continued at that power level. All auxiliary systems of the power plant are working in accordance with their operation needs.
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 981 MWe
· Electricity production since the beginning of the year: 2 379 906 MWh Information on parameters at Unit 2 today on July 10, 2007 at 08:45 o‘clock:
· The Unit is in Mode 1
· Reactor power is 30 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 2 975 006 MWh Václav BROM
ČEZ Group Spokesman Nuclear Power Plant Temelín