Information on NPP Temelín 14/2006

The first Units is operated at a planned power level. Unit 2 is shutdown as planned for the replacement of the high pressure turbine rotor.

January 19, 2006

The first Units is operated at a planned power level. Unit 2 is shutdown as planned for the replacement of the high pressure turbine rotor. All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on January 19, 2006 at 07:15 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 97%
· Turbine generator output - 978 MW
· Electricity production since the beginning of the year: 412 160 MWh

Information on parameters at Unit 1 today on January 19, 2006 at 07:15 o‘clock:
· Unit is in Mode 5
· Reactor power is 0%
· Turbine generator output - 0 MW
· Electricity production since the beginning of the year: 54 079 MWh