20. 7. 2007

Information on NPP Temelín 141 / 2007

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.

July 20, 2007

Information on parameters at Unit 1 today on July 20, 2007 at 10:30 o‘clock:
· Unit is in Mode 1 - power operation · Reactor power is 98 %
· Turbine generator output - 980 MWe
· Electricity production since the beginning of the year: 2 615 392 MWh

Information on parameters at Unit 2 today on July 20, 2007 at 10:30 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 100 %
· Turbine generator output - 1012 MW
· Electricity production since the beginning of the year: 3 165 912 MWh

Ing. Marek Sviták
Spokesman of the CEZ Group Temelín NPP