27. 7. 2007
Information on NPP Temelín 146 / 2007
Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems of the power plant are in operation in accordance with the operational needs of the units.
· Unit is in Mode 1 - power operation · Reactor power is 97 %
· Turbine generator output - 981 MWe
· Electricity production since the beginning of the year: 2 780 195 MWhInformation on parameters at Unit 2 today on July 27, 2007 at 08:30 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 99 %
· Turbine generator output - 1006 MW
· Electricity production since the beginning of the year: 3 334 633 MWhIng. Marek Sviták
Spokesman of the CEZ Group
Temelín NPP