2. 8. 2006
Information on NPP Temelín 149/2006
Shortly before 5 a.m. today, the turbine generator of Unit 2 has been synchronized to the distribution grid. After about twenty minutes of operation, an activation of a turbine technology protection occurred and the turbine has been automatically switched off.
At Unit 1, a planned outage is under way, that is connected with the annual refueling of 1/4 of the reactor fuel. All auxiliary systems are working in accordance with the operation needs of individual units. Information on parameters at Unit 1 today on August 2, 2006 at 07:00 o‘clock:
· Unit is in Mode 3
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 3 450 131 MWh Information on parameters at Unit 2 today on August 2, 2006 at 07:00 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 35 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 4 114 225 MWh Milan Nebesář
NPP Temelín Spokesman