9. 8. 2006
Information on NPP Temelín 155/2006
Unit 2 is in operation at planned power level. At Unit 1, the technicians are carrying out a series of reactor core physics tests. After their termination, they will synchronize the Unit with the distribution grid.
· Unit is in Mode 2
· Reactor power is 1,5 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 3 450 131 MWh Information on parameters at Unit 2 today on August 9, 2006 at 08:30 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 94 %
· Turbine generator output - 945 MWe
· Electricity production since the beginning of the year: 4 254 159 MWh Milan Nebesář
NPP Temelín Spokesman