6. 9. 2007

Information on NPP Temelín 175 / 2007

At Unit 1, a planned outage is under way, that is connected with the annual refueling of ¼ of the reactor fuel. Unit 2 is in operation at planned power level. All auxiliary systems are working in accordance with the operation needs of individual units.

September 6, 2007

Information on parameters at Unit 1 today on September 6, 2007 at 09:30 o‘clock:

· Unit is in Mode 6
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 2 964 775 MWh

Information on parameters at Unit 2 today on September 6, 2007 at 09:30 o‘clock:

· Unit is in Mode 1 - power operation
· Reactor power is 100 %
· Turbine generator output - 1010 MWe
· Electricity production since the beginning of the year: 4 296 780 MWh

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín