8. 9. 2006
Information on NPP Temelín 177 / 2006
Unit 1 is in operation at planned power level. In the evening on Saturday September 9, Unit 1 will be for a short time planned shutdown. The reason of it is the performance of the regular test of the reactor control organs. On Monday September 11 in the morning, the electricity delivery from the unit will be restored.
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 975 MWe
· Electricity production since the beginning of the year: 3 969 705 MWh Information on parameters at Unit 2 today on September 8, 2006 at 08:30 o‘clock:
· Unit is in Mode 6
· Reactor power is 0 %
· Turbine generator output - 0 MWe
· Electricity production since the beginning of the year: 4 609 632 MWh Václav Brom Spokesman of the Temelín NPP